自动排水器用于自动排除管道低处、油水分离器、气罐及各种过滤器底部等处的冷凝水。可安装于不便进行人工排污水的地方,如高处、低处、狭窄处。并可防止人工排水被遗忘而造成压缩空气被冷凝水重新污染。

The automatic drainer is used to automatically drain the condensed water at the lower part of the pipeline, the oil-water separator, the air tank and the bottom of various filters. It can be installed in places where it is inconvenient to manually discharge sewage, such as high place, low place and narrow place. It can also prevent the artificial drainage from being forgotten and causing the compressed air to be re polluted by condensate water.

自动排水器安装步骤

Installation steps of automatic drainer

1:在你开始安装之前应该要做的事是把清洁压缩空气系统里打扫干净,这一步做好了对于我们后面的安装有很大的帮助。

1: Before you start the installation, you should do is to clean the compressed air system. This step is very helpful for our later installation.

20201209667148.jpg

2:在你安装的时候应该注意机器上阀体上面箭头的具体指向,还有出水口千万不要用不抗气流冲击的软管来连接,不让你当你安装完成开始使用一段时间以后你就会发现你的水排不出去了,此时应该就是这个软管脱离了。

2: When you install, you should pay attention to the specific direction of the arrow on the valve body of the machine, as well as the water outlet. Do not use the hose that is not resistant to air impact to connect. When you install and start to use for a period of time, you will find that your water can not be drained out. At this time, it should be that the hose is detached.

3:注意你接入自动排水器的电压大小应该与自动排水器上的额定电压一样,大概也行,但是不能太低也不能高于,就是小于等于了。而且如果你使用直流电的话,那你接入的正极必须得与自动排水器上的接头“1”连接。

3: Note that the voltage you connect to the automatic drainer should be the same as the rated voltage on the automatic drainer. It is probably OK, but it cannot be too low or higher, that is, it is less than or equal to. And if you use direct current, the positive pole you connect to must be connected to the connector "1" on the automatic drainer.

4:如果是出厂的时候就已经接好的排水阀门的话,那我们我们就应该要明白的是此时自动排水器上的褐色导线为火线L,蓝色导线为零线N,黄绿双色的是需要我们完成安装后连接的地线GND。

4: If it is a drain valve that has been connected when leaving the factory, we should understand that the brown wire on the automatic drainer is the live wire L, the blue wire is the zero wire n, and the yellow and green color is the GND ground wire that needs to be connected after the installation.

5:为了防止接线盒上的长螺钉进水烧毁,我们必须得把长螺钉好好拧紧。这里给点自动排水器安装小提示,安装前电源必须为断开状态,还有就是压缩空气得保证完全排空即此时自动排水器中属于零压力状态下。

5: In order to prevent the long screw on the junction box from being burned by water, we must tighten the long screw well. Here are some tips for the installation of the automatic drainer. Before installation, the power supply must be disconnected, and the compressed air must be completely drained, that is, the automatic drainer belongs to zero pressure state at this time.

其实它的安装方法并不是特别难,主要在于安装之前了解关于安装它的一些常识就好,知道了这些小常识后我相信自动排水器的安装已不再是那么的难了,不过鉴于以及使用寿命的问题,小编还是比较觉得找个老师或者自动排水器安装公司来给你全程安装处理要好一点,这样不仅问题得到了解决,重要的是有了安装售后服务的我们以后再也不用担心哪天自动排水器突然不排水了或者哪儿断了出问题了,

In fact, its installation method is not particularly difficult. The main thing is to know some common sense about installing it before installation. After knowing these little common sense, I believe that the installation of automatic drainage device is no longer so difficult. However, in view of the safety and service life, the editor still thinks that a teacher or an automatic drainer installation company will provide you with the whole installation process Better, not only has the safety problem been solved, but also, with the installation of after-sales service, we don't have to worry about the day when the automatic drainer suddenly fails to drain or where it breaks,